On behalf of Rutgers University, ORSP is
responsible for issuing, negotiating and executing subawards/subcontracts on
sponsored projects. A subaward is a legal commitment by Rutgers University
and must be executed by university officials authorized by the Board of
Governors.
In most cases, if a subaward is included in the original grant application
and approved in the budget and award by the sponsor, the competitive bidding
policies will not apply to the subawards. Terms and conditions of the prime
award to Rutgers University will be passed to the subrecipient in the
subaward documents.
Subawards can not be issued until ORSP has received and processed the prime
award to the Rutger PI. ORSP can not issue subawards against an IPAS
account.
In order for ORSP to issue the subaward, the PI must fully complete and
submit via email to the Grant Specialist, the Subaward Checklist, a detailed
scope of work and a budget. The scope of work and budget must be in
accordance with the grant award. Incomplete checklists will be returned to
the sender for completion. The PI should retain a copy of the Subaward
Checklist for future reference.
Subaward
Checklist ( Fillable PDF Updated
7/27/2009)
Elements of the Scope of Work: The Scope of Work is the section of a
subaward that describes the work to be undertaken by the subrecipient, and
including, but not limited to:
- Objective, aims or purpose
- Period of performance
- A general description of the actions to be performed by the
subcontractor and the expected results
- A list of detailed work requirements; list tasks and what is
expected; should provide both technical and performance specifications.
- Performance, quality and timeliness requirements - this includes
required or acceptable levels of performance on each specific task
measured in terms of accuracy, response time, and speed.
- Workload requirements - a description of levels or size of
contractual effort.
- Personnel requirements - minimum qualifications or skill levels
expected in the contractor's staffing.
- Government-furnished equipment and other resources to be furnished
to the subcontractor.
- Reporting requirements - describe any reports to be submitted by the
contractor to show progress.
The grant specialist will prepare the subaward and send it the the
subrecipient’s Research Officer. Any changes to the contract must be
negotiated and approved through the Grant Specialist in ORSP. Upon execution
of the subaward by Rutgers and the subrecipient institution, ORSP will cut
the Purchase Order and distribute copies of the executed subaward to DGCA,
the PI and the subrecipient’s Research Officer. Only upon receipt of a fully
executed subaward should the subgrantee begin work on the project; any work
started prior to receipt of this document is at the risk of the subgrantee.
MANAGING THE SUBAWARD AND MODIFICATIONS
Invoicing and payments: The subgrantee is responsible for invoicing in
accordance with the terms of the subaward. The Rutgers PI is responsible to
sign each invoice. The PI signature certifies that the expenses invoiced are
allowable and in accordance with the scope of work and approval of the work
completed to date. If there is any concern about the invoice or the work
product or progress on the project by the subgrantee, the PI should NOT sign
the invoice. The PI should contact the DGCA accountant or the ORSP Grant
Specialist for guidance. The final invoice submitted by the subgrantee to
Rutgers must be signed by the subgrantee PI and the Rutgers PI. Rutgers may
withhold payment of the final invoice until all reports have been submitted
by the subgrantee.
Modifications: Changes to the subaward must be made in writing via a
subaward modification. Such changes include, but is not limited to,
increase/decrease in funding, extensions of time on the project, changes in
the scope of work, changes in the PI or subgrantee institution or
termination of the subaward. The Rutgers PI must complete the Subaward
Modification Checklist and submit it to the ORSP Grant Specialist via email.
Subaward Modification
Checklist ( Fillable PDF Updated
7/31/2009)
The Grant Specialist will prepare the subaward modification. Upon full
executions, the Grant Specialist will modify the Purchase Order if
necessary, and distribute copies of the modification to DGCA, the PI and the
subrecipient’s Research Officer. Purchase Orders will not be
changed/modified until the subaward has been officially modified.
ARRA Sub Recipient Monitoring
ARRA Subawardee Commitment Form (Fillable PDF Updated 8/24/09)
In order to fulfill federal regulations related to stimulus funding and ARRA subrecipient monitoring, this form must be completed by the subrecipient institution when an ARRA-funded subaward is issued from Rutgers to another institution.
|